EV station shows "Wiring Problem" message

EV Station error message on power up

Product Line:
PTEVC - Electric Vehicle

EV Charging Station installation

The power meter of the unit requires the same phase assignment for the left and right side charging ports.

The message displayed on the screen (LEFT or RIGHT) indicates the side of the station where the incoming power lines should be swapped.
The phase arrangement of L1-L2 must be the same as L3-L4.
Systems using 208Y should arrange breakers accordingly to ensure correct phase usage.