What factory testing is done for Powerpact H, J, and L frame breakers?

Product Line:
Powerpact H, J, L frames

During manufacture and prior to shipping, Powerpact H, J, and L frame breakers receive the following:
  1. Visual inspection of all lugs and operating mechanisms.
  2. Secondary injection testing of all trip units.  Units must trip inside the time-current published trip curve tables.
  3. Calibration of metering features in electronic trip unit to within 2%.
A report may be ordered at the time the breaker is ordered.  
A test report is not on file and is not available if not ordered with the breaker.